ENGCO Electrica signed on July 5, 2016, the contract with Maputo Development Company Sul Ep. to carry out the Tenga electrification project (supply and installation of 3 250 KVA – 33.0.4 KV 33 KV medium voltage network and 9m –Lot 1 Low Voltage Network).
This is the second time we have done resettlement work in Tete where we have done it before, but it was not a medium and low voltage power grid project, nor installation of PTs, it was for mounting lighting at the resettlement of the population in Vila de Cateme , as part of the Vale project.
[ngg_images source=”galleries” container_ids=”1″ display_type=”photocrati-nextgen_basic_thumbnails” override_thumbnail_settings=”0″ thumbnail_width=”240″ thumbnail_height=”160″ thumbnail_crop=”1″ images_per_page=”20″ number_of_columns=”0″ ajax_pagination=”0″ show_all_in_lightbox=”0″ use_imagebrowser_effect=”0″ show_slideshow_link=”1″ slideshow_link_text=”[Show slideshow]” order_by=”sortorder” order_direction=”ASC” returns=”included” maximum_entity_count=”500″]